[ RT ] The last pipe of Russia’s Nord Stream 2 has been welded, operator announces

The last pipe of Russia’s Nord Stream 2 has been welded, operator announces

The final pipe of the Nord Stream 2 pipeline project has been welded and will be lowered into the seabed of the Baltic Sea, the operator of the Russian project, Nord Stream 2 AG, said on Monday.

The final pipe of the Nord Stream 2 pipeline project has been welded and will be lowered into the seabed of the Baltic Sea, the operator of the Russian project, Nord Stream 2 AG, said on Monday.

According to the company, it will now dock the German section with the Danish one and will proceed with pre-commissioning activities with the aim of having the pipeline in operation by the end of 2021.

Last pipe of Nord Stream 2 gas pipeline Photo: Nord Stream 2 / Axel Schmidt / RT

The Nord Stream 2 project consists of two pipelines designed to carry some 55 billion cubic meters of gas per year from the Siberian gas fields in Russia across the Baltic Sea to Germany. The project has seen numerous roadblocks, with the US government threatening the companies and states involved in the construction with sanctions. 

“Nord Stream 2 will contribute to meeting long-term needs of the European energy market for gas imports, improving supply security and reliability, and providing gas under sensible economic conditions,” said Nord Stream 2 AG.